Stone Floor Receiving, Inspection and Handover Checklist

A stone floor handover should connect the approved material and installation system to clear inspection records and care instructions. This checklist focuses on receiving, appearance approval and handover documentation. For pre-installation coordination, use the stone installation planning checklist.

Receive and identify the material

A photograph cannot confirm a stone’s exact name, origin or performance. Where those characteristics matter, use the supplier’s confirmed documentation and the relevant test records.

Approve the appearance before setting

Review the proposed layout under suitable lighting with the responsible client or designer. Agree how colour variation, veining, tile orientation, edges and transitions should be arranged. Use an approved sample range or mock-up when one piece cannot represent the full visual variation.

For floors with a pattern, dry-lay or otherwise review the proposed sequence using a method agreed by the installer and designer. Record the approved layout and any areas that require special matching.

Check the installation records

Ask the installer to identify the approved assembly, supporting construction checks, product instructions and inspection hold points. Moisture test results should state their method and units; percentages, relative humidity and emission rates are different measures and must be assessed against the selected system’s requirements.

Do not use a single friction number, water-drop observation or generic curing period to approve a floor. Confirm the material’s intended use, the installation specification and the responsible professional’s acceptance criteria.

Inspect against agreed criteria

Area What to record
Visual finish Layout, colour range, orientation, visible chips, scratches and agreed repairs
Interfaces Edges, thresholds, transitions, joints and penetration details
Workmanship The project criteria, measurement method, inspected locations and results
Protection and release Applicable product curing requirements, temporary protection and approval before use

Where a check suggests a defect, have the installer or project professional investigate it. A hollow sound or surface mark alone does not establish its cause or the appropriate remedy.

Prepare care and handover information

Confirm whether a sealer is appropriate for the actual material and installation. Test compatibility as directed by the product manufacturers rather than assuming every stone needs the same treatment.

Resources and material references

For technical installation references, consult the applicable TCNA Handbook and the selected product manufacturers’ instructions through the project professionals. For appearance ideas, see our real stone applications in China; these photos are visual references, not specifications for a new floor.

Discuss stone floor material requirements with your drawings, finish, quantity and destination.